Summer measures at concrete plants are taken depending on the climatic conditions, especially when the ambient temperature rises above +30 °C for several consecutive days, or in the event of intense sunlight, low relative humidity or strong wind. In common concrete practice, the recommended upper limit for the temperature of fresh concrete is considered to be 30 °C. If this is exceeded, it is advisable to take special technological measures or, by agreement of all construction participants, move the concreting to more favorable climatic conditions. At high outdoor temperatures, the temperature of fresh concrete also reaches values of around 30 °C. During transport and especially during pumping, the temperature of fresh concrete may further increase due to friction of the concrete mixture against the walls of the pipe. Higher concrete temperature accelerates cement hydration, shortens the workability time of the concrete mixture, increases the risk of loss of consistency and promotes the evaporation of water from fresh concrete.
The greatest risk of concreting at high temperatures is the rapid evaporation of water, which can cause plastic shrinkage cracks, increased shrinkage and subsequent deterioration of the mechanical properties and durability of the concrete structure. For this reason, it is necessary to pay increased attention to the production, placement and subsequent treatment of the concrete mixture.
According to the standards ČSN EN 206+A2, ČSN P 73 2404 and ČSN EN 13670, concrete must be produced, transported, placed and treated in such a way that its required properties are maintained. Although these standards do not specify the maximum permissible temperature of fresh concrete, they require the adoption of appropriate technological measures in adverse climatic conditions, in particular:
- limiting the overheating of aggregates by appropriate storage or sprinkling it with water
- minimizing the time between production and placement of the concrete mix
- using a higher consistency level (S4, S5) when pumping concrete
- using suitable superplasticizing additives or additives that extend workability (retarder) - consultation required before concreting
- strictly avoiding additional addition of water on the construction site
- immediately starting concrete treatment after completion of surface treatments
- using sprinkling, geotextiles, foil or suitable spray-on paraffin-based treatment agents
- ensuring a sufficiently long treatment time with regard to climatic conditions, cement used and the nature of the structure
For concreting carried out on ŘSD ČR construction sites at ambient temperatures above 30 °C, TKP 18 requires the processing of technological concreting procedure and subsequent treatment of the concrete. This procedure must be approved by the investor or the construction site's technical supervision (TDS) before concreting begins and its use must be recorded in the construction log. The first hours after placing are the most critical period in terms of concrete quality. It is necessary to prevent premature drying of the surface, because the resulting plastic shrinkage cracks cannot be removed later.
With expected daily temperatures exceeding 30 °C, we recommend planning concreting sufficiently in advance and consulting the dispatcher and technologist of the concrete plant regarding their preparation.
The guaranteed workability time of fresh concrete is 90 minutes (at +1 °C to +25 °C). The guaranteed workability time of concrete outside standard climatic conditions is 45 minutes. The processing time of the fresh concrete mixture begins with mixing cement with water (the time is always indicated on the DL) and lasts for the entire period of placing - according to Art. VIII – Product properties and documentation - point 8.
For larger concreting works, we recommend starting work in the early morning hours and preparing all means for immediate concrete treatment before starting concreting.
The customer of the concrete mix is obliged to ensure the conditions for proper placement, compaction and subsequent treatment of fresh concrete. Failure to comply with these principles may lead to the formation of plastic shrinkage cracks, increased shrinkage, reduced durability of the structure and other defects, even though the concrete mix was produced in accordance with the requirements of ČSN EN 206+A2 [N1]. In the event of extreme climatic conditions, when it will not be possible to ensure the delivery of a concrete mix with the required properties even after taking normal technological measures, the customer will be informed in a timely manner. If the concreting continues despite this warning, the customer assumes responsibility for the conditions of placement and treatment of the concrete mix on the construction site. In such a case, ZAPA beton, a.s. is not liable for defects resulting from failure to comply with the technological principles of concreting at high temperatures.